How Existing Procurement Law Can Keep Kenya's Geothermal Wells on Schedule
New policy analysis by Moses Kilimo: How Existing Procurement Law Can Keep Kenya's Geothermal Wells on Schedule, without a new fund or an exemption.

Executive Summary
A geothermal well test cannot wait for procurement. When a downhole logging tool or other time-critical equipment fails, Kenya's Geothermal Development Company (GDC) needs replacements within weeks, but an open tender runs for months, so wells are measured late or poorly and the results shape the equipment built around them. This analysis argues that the fix already exists in Kenya's Public Procurement and Asset Disposal Act. A framework agreement under section 114 can cover recurring multi-vendor items, competed once in the open, while section 103(2)(d) allows direct procurement of proprietary parts for standardisation or compatibility, within strict conditions. Neither needs a new fund, an exemption, Cabinet or Parliament. The decision sits with GDC's accounting officer, inside an existing budget.
Key Findings
Geothermal well tests need replacement equipment within weeks, but open tenders typically take months.
GDC's public tender record shows recurring needs for well logging and testing equipment met through repeated one-off tenders.
Kenya's National Infrastructure Fund suits financing new well fields but cannot replace a failed tool during a testing window.
A framework agreement under section 114 of the Public Procurement and Asset Disposal Act can cover recurring multi-vendor items for up to three years.
Section 103(2)(d) allows direct procurement of proprietary parts for standardisation or compatibility, subject to strict conditions and prior written approval.
A framework competed once in the open leaves a cleaner audit trail than repeated urgent single-supplier purchases.
The decision sits with GDC's accounting officer, within a budget its steam sales already sustain.
A geothermal well test cannot wait for procurement. Once a new well has been drilled and allowed to heat up, its output must be measured with downhole logging tools before anyone designs the steam gathering system around it. When a depth encoder fails or a cable is damaged, the unit stops producing reliable logs. The replacement parts are often proprietary, and the field team needs them within weeks.
An open tender runs in months. Moses Kilimo, a reservoir engineer and ETA Fellow, argues that when the two clocks collide, the well is measured late or measured poorly, and those measurements become the basis on which separators and pipelines are sized. His Signature Analysis shows that Kenya's procurement law already contains the fix.
A recurring need met by one-off tenders
The Geothermal Development Company's public tender record shows the pattern. Well logging and testing equipment went to tender in 2021/2022 and had to be re-tendered. A further open tender for logging tools and accessories followed in May 2025. Each was a one-off process for equipment whose need recurs.
The same mechanism reaches into drilling. A string stuck in the hole may need fishing tools or left-hand drill pipe that few programmes stock. Every day of waiting lowers the chance of recovery, and a long enough wait can force the hole to be abandoned. The analysis does not rest on a count of incidents. It rests on the structure of the problem: recurring needs met by one-off procurements.
Why a new fund is the wrong tool
Kenya's National Infrastructure Fund, created in 2026, is designed to mobilise pension funds and other private capital for infrastructure. Every investment needs an approved feasibility study, and the Fund's investment policy passes through Cabinet and Parliament. That machinery suits financing a new well field. It cannot replace a depth encoder while a testing window is still open.
Two routes already in the Act
The Public Procurement and Asset Disposal Act offers two routes, and GDC needs both.
The first is a framework agreement under section 114. Where quantities cannot be predicted, an entity can run one open tender against at least seven vendors and hold the agreement for up to three years. GDC could then call off logging accessories, survey tools, testing consumables and drilling contingency items at prices already fixed, without re-running a tender each time something fails.
The second covers what a framework cannot. Proprietary parts made only by the original manufacturer do not suit a seven-vendor competition, which can simply put an intermediary between GDC and the maker, at a mark-up. Section 103(2)(d) allows direct procurement from an existing supplier for standardisation or compatibility, within strict conditions on size, price and the absence of an alternative. Each purchase needs the accounting officer's prior written approval under the 2020 Regulations, leaving a dated record.
The urgent-need ground is the weakest option. Once failures recur across two fields, the next one starts to look foreseeable.
The cleaner answer on corruption
The concern that tenders invite graft is well founded, and it argues for the framework route. A framework is competed once, in the open, and every call-off traces back to it. An urgent-need claim is a single-supplier negotiation approved under pressure.
KenGen's experience adds one discipline. In 2026, the High Court upheld a review board decision requiring KenGen to verify disputed manufacturer authorisations on a compressor spares tender. Any framework GDC runs should confirm authorisations with the manufacturer before award, not after.
An internal decision, inside an existing budget
GDC earns about KSh 3 billion a year from steam sold to KenGen at Olkaria, and a framework agreement would cost a small fraction of that. The proposal asks for no new capital from Treasury or any financier. The decision sits with GDC's Managing Director & CEO as accounting officer, who can delegate call-off authority in writing to the field departments under section 69(4) while keeping accountability in place.
The stakes reach beyond one well. A developer that can show financiers a clean resource record, gathered on schedule, is a more bankable counterparty, a point that runs through how African energy projects reach financial close. The same template could serve KenGen and Kenya's transmission company without new legislation, and it reflects the institutional capability Africa's energy transition depends on.
The analysis is not a substitute for formal legal advice. It offers a tested starting position: the statutory basis exists, and it does not need Cabinet or Parliament to say yes.
The full analysis, including the governance figure, the statutory analysis and complete references, is available to download.